Commissioning of the unit 4 of Korean Shin Kori nuclear plant delayed

11/08/2017 10:02 Nuclear

news

The finalization of the unit 4 of the Shin Kori nuclear power plant has been postponed by ten months due to design enhancement and additional seismic assessment work. The operation of the plant is now expected to start in 2018.

The unit 4 of the nuclear plant underwent hydrostatic testing and hot functional testing in November 2015 and April 2016 respectively. Korea Hydro and Nuclear Power (KHNP) is planning on loading fuel into the reactor next January, and expects commercial operation to start in September.


The approval for the construction of the first pair of APR1400 reactors - Shin Kori 3 and 4 – has been given in 2006, even though the actual construction licence was not issued until April 2008.

 

Unit 3 was initially scheduled to enter commercial operation at the end of 2013, with unit 4 due to launch in September 2014. Nevertheless, their operation was deferred by the necessity to test safety-related control cabling and its subsequent replacement. Finally, Unit 3 was connected to the grid in January 2016 and entered commercial operation in December.

 

Two more units of the 1350 MWe pressurized water reactors are being currently developed as units 1 and 2 of the Shin Hanul site in South Korea, which are forecast to start operating in April 2018 and February 2019 respectively.
 

Turkey is the second consumer of autogas globally

18/10/2017 16:18:00

Turkey is the second consumer of autogas globally

<READ MORE

UK has enough power for consumers this winter, says National Grid

18/10/2017 13:47:00

UK has enough power for consumers this winter, says National Grid

READ MORE

EU compelled by IETA to complete Emission Trading System

18/10/2017 13:37:00

EU compelled by IETA to complete Emission Trading System

READ MORE