Novovoronezh II-2 cleared for launch

15/04/2019 09:03 Nuclear

news

Unit 2 of the Novovoronezh II nuclear power plant in southwest Russia started the process of physical launch yesterday after having received regulatory approval to do so, Rosenergoatom, the operator subsidiary of state nuclear corporation Rosatom, has announced. The VVER-1200 reactor was brought to the minimum controlled power level on 22 March.

Director of the plant, Vladimir Povarov, said that obtaining a permit from Rostechnadzor meant that preparation for the physical start-up phase had been fully completed.

 

"The actual values of the neutron-physical characteristics of the reactor core correspond to the design ones and so we can now proceed to the next stage, the energy start-up," Povarov said.

 

This stage involves gradually increasing the reactor's power from 1% to 35-40% in several stages. Rosenergoatom said that this power level enables connection of the turbogenerator to the network and the start of electricity generation, which is scheduled for next month. There will then be the long process of increasing the power level to 100%. Commissioning of the unit is scheduled before the end of the year.

 

Novovoronezh II-2 will be the third VVER-1200 to be commissioned, following Novovoronezh II-1 and Leningrad II-1, which were launched in 2016 and 2017, respectively.

Source: world-nuclear-news.org

Daily (12.12.2019): Brent crude down 1% on Wednesday following an unexpected increase in crude inventories

12/12/2019 11:48:00

Oil futures ended lower on Wednesday after U.S. government data indicated a surprise increase in domestic supply in crude oil, as well as important gains in gasoline and distillate inventories. Brent crude for February delivery slipped by 62 cents, or around 1% to settle at $63.72 a barrel. WTI crude for January delivery declined 48 cents, or 0.8%, to close at $58.76 a barrel.

<READ MORE

Botas issues large tender for 30 LNG cargoes

12/12/2019 08:55:00

Turkish oil and gas pipeline operator Botas is reportedly seeking 30 liquefied natural gas (LNG) cargoes for delivery over December 2019 to March 2020.

READ MORE

Germany's EEG levy surplus decreased to €1.71 billion in November

12/12/2019 08:53:00

The German EEG levy account, which funds Germany’s renewable energy programs, had a cumulative surplus of €1.71 billion ($1.89 billion) at the end of November. This is a small decrease of around €24 million compared to October.

READ MORE