Olkiluoto EPR start-up delayed by final checks

11/11/2019 10:17 Nuclear

news

Areva-Siemens has told TVO the final verification of the mechanical, electrical and the instrumentation and control (I&C) systems has to be done carefully and to a high standard.

In an updated schedule provided to TVO in July, the supplier said nuclear fuel was to be loaded into the reactor in January 2020, the first connection to the grid to take place in April 2020, and the start of regular electricity production was to take place in July 2020.

 

"Although the completion of the plant will be further delayed, we are very close to reaching the fuel loading phase and start-up of the OL3 EPR unit," said Jouni Silvennoinen, TVO's director for the project. The utility is currently preparing for the loading of fuel, he added.

 

OL3 plant supplier consortium - Areva GmbH, Areva NP SAS and Siemens AG - is constructing the unit under a fixed-price turnkey contract. They have joint liability for the contractual obligations until the end of the guarantee period of the unit.

 

The consortium began construction of Olkiluoto 3 in 2005. Completion of the reactor was originally scheduled for 2009, but the project has had various delays and setbacks.

 

TVO was granted an operating licence by the Finnish government for Olkiluoto 3 on 7 March. For fuel loading, TVO still requires a separate authorisation from the country's Radiation and Nuclear Safety Authority.

Source: world-nuclear-news.org

Daily (09.12.2019): Brent posts a 3.1% weekly gain following OPEC decision to reduce output target

09/12/2019 12:49:00

Crude oil prices soared on Friday as OPEC+ agreed in Vienna to extend output cuts by 500,000 barrels per day in early 2020. Consequently, Brent crude rallied by $1, or 1.6%, to settle at $64.39. It recorded a weekly hike of 3.1%. U.S. WTI crude rose by 77 cents, or 1.3%, to $59.20 per barrel. For the week, WTI jumped 7.3%, after a 4% rise reached on Wednesday after data indicated sharp declines in U.S. crude inventories.

<READ MORE

Vestas books 137MW US tour

09/12/2019 09:06:00

Vestas has received a turbine order totalling 137MW from an unnamed client for an undisclosed wind farm in the US.

READ MORE

Russian company to initiate feasibility study of undersea gas pipeline in 2020

09/12/2019 09:01:00

Russian company Gazprom is set to initiate the feasibility study in the first quarter of 2020 for laying down undersea pipeline starting from Persian Gulf to Pakistan, India and Bangladesh initially that will ultimately end to China after touching Myanmar and Thailand, a senior official of the Petroleum Division privy to the development told The News.

READ MORE