Voltalia starts construction of transmission line in Brazil for 2-GW wind cluster

08/02/2019 09:28 Renewable

news

French renewable power plants operator Voltalia SA announced on Thursday it has commenced the construction works on a 500-kV transmission line that will enable connecting 2 GW of wind power generating capacity.

The works, which also include a new substation, will connect the Serra Branca cluster in Rio Grande do Norte to the national network. Among the plants being currently developed are the 163-MW Ventos da Serra do Mel 1 and the 128-MW Ventos da Serra do Mel 2, in addition to the 252 MW sold to Actis in 2018.

 

The commissioning of transmission facilities is expected to be completed by the end of 2019. After overseeing the construction, Voltalia will also be responsible for operation and maintenance (O&M) services, the company said.

 

In Brazil, Voltalia has 724 MW under construction or operation and a total of 2.7 GW in development.

Source:renewablesnow.com

Daily (21.05.2019): European spot power prices soared by around 16% due to firmer consumption

21/05/2019 10:04:00

Oil prices diverged on Monday. OPEC’s intention to maintain output cuts coupled with the escalating tensions in the Middle East sent WTI futures up by 0.5% at 63.10 USD/bbl. Meanwhile, Brent crude lost 0.3% to settle at 71.97 USD/bbl, influenced by the high level of global crude oil inventories.

<READ MORE

Gazprom discovers 2 new fields containing over 500 billion cu m of gas on Yamal shelf

21/05/2019 09:10:00

The Federal Agency for Mineral Resources approved the expert opinions of the State Reserves Commission with regard to the discovery by Gazprom of new hydrocarbon fields on the shelf of the Yamal Peninsula, namely the Dinkov and Nyarmeyskoye fields.

READ MORE

Vestas gets 249-MW turbine order for Texas project from EDF Renewables

21/05/2019 09:06:00

EDF Renewables has ordered more turbines from Vestas Wind Systems A/S for the 273-MW Las Majadas wind project in Texas, the supplier announced today.

READ MORE