Voltalia starts construction of transmission line in Brazil for 2-GW wind cluster

08/02/2019 09:28 Renewable

news

French renewable power plants operator Voltalia SA announced on Thursday it has commenced the construction works on a 500-kV transmission line that will enable connecting 2 GW of wind power generating capacity.

The works, which also include a new substation, will connect the Serra Branca cluster in Rio Grande do Norte to the national network. Among the plants being currently developed are the 163-MW Ventos da Serra do Mel 1 and the 128-MW Ventos da Serra do Mel 2, in addition to the 252 MW sold to Actis in 2018.

 

The commissioning of transmission facilities is expected to be completed by the end of 2019. After overseeing the construction, Voltalia will also be responsible for operation and maintenance (O&M) services, the company said.

 

In Brazil, Voltalia has 724 MW under construction or operation and a total of 2.7 GW in development.

Source:renewablesnow.com

Daily (15.04.2019): Brent crude climbed by 1% on upbeat Chinese economic data and tight global supply

15/04/2019 11:24:00

Oil prices added gains on Friday following a recovery in Chinese exports last month. The rising U.S. and euro zone bond yields to three-week highs and German growth forecasts also supported prices. Furthermore, involuntary cuts in Venezuela supply and Iran signaled another lift in prices. Brent crude hiked by 1% to $71.55 a barrel , while WTI futures rose by 0.5% to $63.89 a barrel.

<READ MORE

Novovoronezh II-2 cleared for launch

15/04/2019 09:03:00

Unit 2 of the Novovoronezh II nuclear power plant in southwest Russia started the process of physical launch yesterday after having received regulatory approval to do so, Rosenergoatom, the operator subsidiary of state nuclear corporation Rosatom, has announced. The VVER-1200 reactor was brought to the minimum controlled power level on 22 March.

READ MORE

Hungary Offers to Buy 25% of LNG Terminal on Krk

15/04/2019 08:59:00

The Hungarian government has made an offer to buy 25 percent of a LNG terminal that is to be built in Croatia, Hungarian Foreign Minister Peter Szijjarto told journalists in Dubrovnik on Friday, according to MTI news agency.

READ MORE